Project Update: Redmond Ridge #113

PU Redmond 113

The largest building to-date in the Redmond Ridge Business Park, Building #113 is a 129,687 warehouse with a 24’ clear height. In January 2020, project teams are wrapping up roof structure, beginning interior work as well as storefront installation.

Sitework included the clearing of the 8.75 acre site which logged 100,000 MBF of timber. The site grade also resulted in a cut-to-fill of 10-15’ on the west side of the site, and 20’ of fill to the east and a 20’ retaining wall on the NE corner of the site. The 570’ long building will have 14 dock doors, 2 on grade drive-in doors, a 7” slab and will be constructed with 60 tilt-panels. This project is currently under construction and is due for completion in early 2020.

This is the eleventh building Sierra has constructed since 2006 in the commercial district of the Redmond Ridge community, which includes warehouse and office buildings.

On the Subject

New Project: Big Eddy Commerce Center
Project Updates
New Project: Big Eddy Commerce Center

Sitework began last year on this 135,387 square foot tilt-up commerce center on 7.5 acres in Gresham, Oregon. ‘Big Eddy’ will have a 30′ clear height, 30 dock...