Project Completion: Portside 55 North

PC Portside North

The first phase of Avenue 55’s Portside 55 (known as ‘Portside 55 North’) has been completed.

This phase included the construction of two buildings, which total 207,000 square feet.

Building A: 155,000 square feet
Tilted using 82 wall panels and 11 ramp panels

Building B: 51,900 square feet
Tilted using 48 building panels and 8 ramp panels

The two buildings share a 175,000 square foot truck court.

Project Team:
Owner/Developer: Avenue 55
Architect: NELSON formerly CRAFT Architects
Civil Engineer: Barghausen Engineers
Contractor: Sierra Construction Company, Inc.
Brokers: Scott Price and Joel Jones, Neil Walter Company

The second phase, known as Portside 55 South, consists of 221,000 square foot Building C. This building is set for completion later this year.

On the Subject

$46M Safeway center opens in Canyon Park
Project Updates
$46M Safeway center opens in Canyon Park

Safeway has opened a lifestyle shopping center in the Canyon Park area of Bothell. Property Development Centers, a wholly owned subsidiary of Safeway Inc., dev...

Continue Reading