office jan

Hot dang! Now it's looking like a office building. The concrete finishing for the floors has begun, crews are running overhead power and installing HVAC, and the siding installation is in full swing! So many things going on - we are in the home stretch!

office jan 9
office jan 17
office jan 8
office jan 15

On the Subject

The Village at Beardslee Crossing
Project Updates
The Village at Beardslee Crossing

Using a multifaceted approach in the design of the project, the developers selected four prominent Bothell individuals to educate visitors on Bothell’s history,...